HI,
I have a conveyor system with diverters and would like to have empty totes created at a point then have these totes visiting different stations (diverters/pushers) depending on an excel/CSV file that tells which stations each tote needs to visit (can be more than one) and at the end a packaging/shipping station will empty all the totes and put them back in line to continue until all orders on the excel sheet are completed. I have tried using the excel reader component but was not successful. can you please help me or share a simulation that uses the excel reader for routing so I can understand how it works.
thanks
Hi,
Would something like this work in conjunction with PM?
If you want to use pure conveyor logic it might get a bit more iffy.
br,
Lefa
will check it thanks