I imported a 3D geometry as the robot gripper and want to set the better visual effect when it’s picking products, so I adjusted the location of I the tool of TCP and the tool1.
For the robot routine from ST02 to ST03,
Firstly, I used the automatic Robot Motion, everything was fine, so I recorded the T1 routine and add one more motion named “Additional 1” just for better logic (see from below picture)
It has trapped me for days, I have thought of the tools reason, but I don’t know how to correct it. Could anyone help to solve this or give me some guidelines? The model is attached here. Thanks in advance!
First, I modified the process so that the gripper is able to pick up the part before moving to the next node.
The issue was resolved by adjusting the MainFrame position of the ST02 Process Node.
It appears that, in the original file, when the generated part was separated from the other part, it overlapped with the Process Node, which caused the problem.
Hi HyeokcheolKwon, thanks for your answer, after I adjusted the Main Frame of the process node, the robot successfully picked the part.
But after that when the ST03 finished processing, the robot no longer doing tasks, did any setup took the robot as a resource and didn’t release it? Thank you in advance!
I found the cause of the issue. It was related to the Simple Robot Pedestal and the Robot Transport Controller.
Currently, the IRB robot is attached to both the Pedestal and the Controller. In this configuration, it seems that the robot is recognized as existing in two different locations.
In addition, because the Pedestal and the Controller had different rotation angles, the robot did not operate correctly.
I set the Controller’s rotation angle to match the Pedestal’s angle (approximately -60°) and then removed the Pedestal component.
After making these changes, the robot operated correctly.
I have attached the modified file for your reference.